11.01.2022

Oslo T-bane CBTC-Project

After two tendering rounds with, at first, four tenderers, Sporveien, the operator of Oslo City’s public transport system, awarded the contract for equipping the metro with a CBTC system to Siemens. R+R has edited the price formats, evaluated the commercial tenders, and supported the negotiations. At the same time, in the Datalink sub-project, Sporveien procures the communication services and the necessary upgrading of the communication infrastructure.

01.11.2021

A1, Extension of the Zurich Northern Bypass

Twenty years ago, a serious fire disaster occurred in the Gotthard motorway tunnel. To commemorate this event, the «SRF Aktuell» TV program has produced a report on road tunnel safety in Switzerland, which was broadcast on October 21, 2021. Many lessons have been learned from this disaster. By using the third tube of the Gubrist tunnel, now under construction, as an example, the FEDRO project managers explain recent developments concerning the safety of road tunnels.

Tunnelsicherheit 20 Jahre nach dem Gotthardunglück

24.08.2021

A1, Extension of the Zurich Northern Bypass

The main construction work for the Weiningen motorway exit and the covered road section will start on August 16, 2021. The Weiningen exit will be relocated and moved around 200m closer to the Limmattalerkreuz junction. In addition, all three Gubrist tunnel tubes will be extended by a new 100m covered motorway section. This will reduce the noise and pollution levels of the adjacent residential areas. From mid-August, the top pavement layer of the roadway in the new third Gubrist tunnel tube will be installed over a period of approximately 3 weeks. Thus, most of the construction work will have been completed. In autumn 2021, installation of the traffic control and safety systems for the third Gubrist tunnel tube will start.

05.07.2021

R+R has moved

Since June 1, 2021, the R+R offices have been moved into new premises on the 6th floor of the Duplex building in Baden at Brown Boveri Strasse 12. As before, we are still at a very central location within the city of Baden. As you notice, we also took the opportunity to update our website. We hope you enjoy the new content, and we look forward to welcoming you in our new offices at the next opportunity.

News
11.01.2022
Oslo T-bane CBTC-Project
01.11.2021
A1, Extension of the Zurich Northern Bypass
24.08.2021
A1, Extension of the Zurich Northern Bypass
05.07.2021
R+R has moved
Federal Roads Office (FEDRO)

MOTORWAY MAINTENANCE PROJECT A1 EFFRETIKON – OHRINGEN

A 12 km stretch of the A1 motorway between the exits Effretikon and Winterthur Ohringen is to be refurbished. Moreover, by introducing up-do-date signalling technology, an optimisation of the traffic flow on the section Winterthur Töss – Winterthur Nord junction is to be achieved.

Stretching an approximate 12 kilometers in length, the A1 motorway section between Effretikon exit and Winterthur Ohringen exit ranks among the most congested motorway sections in the Swiss motorway network. The number of vehicles using it amounts to 100‘000 per day. The section in question has been in continuous service since 1974 and no significant restorative measures have been undertaken since then. In the context of the maintenance project «A1 Effretikon – Ohringen», the section is thus going to be refurbished in the coming years. In particular, there will be a renewal of parts of the roadway and the operation and security installations, in order to comply with current regulatory standards. Additionally, several adjacent structures require corrective maintenance measures to be carried out to warrant full operability of the constructions until the end of their expected life spans.

The FEDRO aims to effectuate a smoothing out of the traffic flow in the Winterthur area by installing up-to-date signalling technology. The project at hand will see to the implementation of according measures between the Winterthur Töss exit and the Winterthur Nord junction. Work on preliminary maintenance measures is set to begin in mid-May 2019. The principal part of the corrective maintenance will be carried out from 2020 to 2022. As part of a set of precursory measures, the Töss Bridge, the overpasses Zürcherstrasse Süd and Grafstal, three structures at the Effretikon exit, the retaining wall Pfahlwand Rossberg and the traffic light system Salomon- Hirzel-Strasse were refurbished between 2015 and 2017. Total project costs amount to 228 Mio. Swiss francs.

Holding mandates as project-owner support unit and construction supervisor, R+R supports and advises the general project management team of the Federal Roads Office in project management, controlling and the assessment of selected issues for the entire duration of the project.

Key data

Client
Federal Roads Office (FEDRO)

Processing period
2020 – 2022

Project costs
approx. 228 Mio. CHF

Project type
Road

Services
Project Management

Fields of expertise
Strategic Planning
Project Planning and Organization
Project Controlling
Procurement
Professional Support
Communication Support

Downloads
Project sheet

Contact

Christoph Marti

Consultant, managing director, member of the board of directors