07.02.2024

N01.22 Motorway section Schönbühl – Kirchberg, Lindenrain rest area upgrade

The service building at the Lindenrain motorway rest area has been equipped with a new toilet module made of chrome steel; construction was completed at the end of 2023. The new toilet module offers better protection against vandalism, and it will be possible to continue its use in the event of a future replacement of the service building. R+R supported the Federal Road Office’s overall project manager in project planning and execution.

12.01.2024

ERTMS Netherlands

Other countries, same problems: Modern railway technology requires time and money to implement. Jost Lüking was member of a team of six European experts on the ETCS train control system who assessed the status of the national ETCS program for the Dutch Parliament in mid-2023. Our Second Opinion formulated recommendations on program governance and management, on the technical, spatial and temporal scope of the program, on system integration and integration management, and last but not least on program costs and their current forecast. The Dutch Ministry of Infrastructure and Waterways published the Second Opinion at the beginning of November.

01.11.2023

EP Hagnau – Augst N02

Within the Hagnau – Augst motorway maintenance project, structural changes to the western tunnel portal (direction Basel/Germany) have to be carried out to enable longitudinal ventilation in both traffic directions. We are pleased that the plans for the extension of the western portal of Schweizerhalle tunnel have officially been approved. This allows us to finalise the detailed design and approach the contractor submission process according to our project schedule.

07.07.2023

N06.28 NEB EM Lyss Süd – Schönbühl

We are pleased to provide managenent support and construction site management for the N06.28 NEB EM Lyss Süd - Schönbühl motorway maintenance project on behalf of the Federal Road Authority’s Thun branch. The project includes replacement of the pavement as well as extensive measures on the engineering structures. The construction work is scheduled to be carried out between 2025 and 2027.

News
07.02.2024
N01.22 Motorway section Schönbühl – Kirchberg, Lindenrain rest area upgrade
12.01.2024
ERTMS Netherlands
01.11.2023
EP Hagnau – Augst N02
07.07.2023
N06.28 NEB EM Lyss Süd – Schönbühl
Federal Roads Office (FEDRO)

MOTORWAY MAINTENANCE PROJECT A1 EFFRETIKON – OHRINGEN

A 12 km stretch of the A1 motorway between the exits Effretikon and Winterthur Ohringen is to be refurbished. Moreover, by introducing up-do-date signalling technology, an optimisation of the traffic flow on the section Winterthur Töss – Winterthur Nord junction is to be achieved.

Stretching an approximate 12 kilometers in length, the A1 motorway section between Effretikon exit and Winterthur Ohringen exit ranks among the most congested motorway sections in the Swiss motorway network. The number of vehicles using it amounts to 100‘000 per day. The section in question has been in continuous service since 1974 and no significant restorative measures have been undertaken since then. In the context of the maintenance project «A1 Effretikon – Ohringen», the section is thus going to be refurbished in the coming years. In particular, there will be a renewal of parts of the roadway and the operation and security installations, in order to comply with current regulatory standards. Additionally, several adjacent structures require corrective maintenance measures to be carried out to warrant full operability of the constructions until the end of their expected life spans.

The FEDRO aims to effectuate a smoothing out of the traffic flow in the Winterthur area by installing up-to-date signalling technology. The project at hand will see to the implementation of according measures between the Winterthur Töss exit and the Winterthur Nord junction. Work on preliminary maintenance measures is set to begin in mid-May 2019. The principal part of the corrective maintenance will be carried out from 2020 to 2022. As part of a set of precursory measures, the Töss Bridge, the overpasses Zürcherstrasse Süd and Grafstal, three structures at the Effretikon exit, the retaining wall Pfahlwand Rossberg and the traffic light system Salomon- Hirzel-Strasse were refurbished between 2015 and 2017. Total project costs amount to 228 Mio. Swiss francs.

Holding mandates as project-owner support unit and construction supervisor, R+R supports and advises the general project management team of the Federal Roads Office in project management, controlling and the assessment of selected issues for the entire duration of the project.

Key data

Client
Federal Roads Office (FEDRO)

Processing period
2020 – 2022

Project costs
approx. 228 Mio. CHF

Project type
Road

Services
Project Management

Fields of expertise
Strategic Planning
Project Planning and Organization
Project Controlling
Procurement
Professional Support
Communication Support

Downloads
Project sheet

Contact

Christoph Marti

Consultant, Project manager, managing director, member of the board of directors