07.02.2024

N01.22 Motorway section Schönbühl – Kirchberg, Lindenrain rest area upgrade

The service building at the Lindenrain motorway rest area has been equipped with a new toilet module made of chrome steel; construction was completed at the end of 2023. The new toilet module offers better protection against vandalism, and it will be possible to continue its use in the event of a future replacement of the service building. R+R supported the Federal Road Office’s overall project manager in project planning and execution.

12.01.2024

ERTMS Netherlands

Other countries, same problems: Modern railway technology requires time and money to implement. Jost Lüking was member of a team of six European experts on the ETCS train control system who assessed the status of the national ETCS program for the Dutch Parliament in mid-2023. Our Second Opinion formulated recommendations on program governance and management, on the technical, spatial and temporal scope of the program, on system integration and integration management, and last but not least on program costs and their current forecast. The Dutch Ministry of Infrastructure and Waterways published the Second Opinion at the beginning of November.

01.11.2023

EP Hagnau – Augst N02

Within the Hagnau – Augst motorway maintenance project, structural changes to the western tunnel portal (direction Basel/Germany) have to be carried out to enable longitudinal ventilation in both traffic directions. We are pleased that the plans for the extension of the western portal of Schweizerhalle tunnel have officially been approved. This allows us to finalise the detailed design and approach the contractor submission process according to our project schedule.

07.07.2023

N06.28 NEB EM Lyss Süd – Schönbühl

We are pleased to provide managenent support and construction site management for the N06.28 NEB EM Lyss Süd - Schönbühl motorway maintenance project on behalf of the Federal Road Authority’s Thun branch. The project includes replacement of the pavement as well as extensive measures on the engineering structures. The construction work is scheduled to be carried out between 2025 and 2027.

News
07.02.2024
N01.22 Motorway section Schönbühl – Kirchberg, Lindenrain rest area upgrade
12.01.2024
ERTMS Netherlands
01.11.2023
EP Hagnau – Augst N02
07.07.2023
N06.28 NEB EM Lyss Süd – Schönbühl
Banedanmark

SIGNALLING PROGRAMME – FINANCIAL MANAGEMENT

Banedanmark, the Danish railway infrastructure organisation, is planning a full replacement and reorganisation of safety technology throughout its entire network. The European signalling standard, ERTMS Level 2, is to be introduced across the entire area of the long-haul rail network. The Copenhagen S-Bane is to be equipped with a new CBTC signalling system, in line with the state of the art for suburban railways, which should also enable fully automated train operation at a later stage. The operational management will be brought together in three new traffi c control centres; the interlocking technology will be entirely replaced and will also undergo further centralisation. The new organisation must be prepared and trained to implement and operate the Signalling Programme.

In 2007 – 2008, a pre-project was developed as the basis for the fi nal political decision. Managing the investment and budgeting workstream, R+R developed the system defi nition for the cost estimate, compiled price catalogues, estimated the costs for the long-haul railway and S-Bane and compared them with previous cost estimates, calculated the annual appropriations for various migration strategies, and carried out strategic cost comparisons of technological alternatives.

From 2009 – 2012, R+R handled the commercial procurement of the main system contracts (S-Bane, Fjernbane East and West, Onboard), set up tender documents, evaluated off ers and led negotiations with bidders. Additional procurement procedures followed, e.g. for train radio, interface systems and fi xed telecommunications installations. In accordance with the awarded contracts, the budget was adjusted for two additional political milestones. From 2012 onwards, R+R tracked cost developments and led strategic studies on programme extensions. Among other things, R+R supervised the Business Case for (semi-) automatic train operation.

Key data

Client
Banedanmark

Processing period
2007 – 2017

Project costs
CHF 3.1 billion

Project type
Rail

Services
Consulting

Fields of expertise
Project Evaluation
Comparative Market Studies

Downloads
Project sheet

Contact

Dr. Jost Lüking

Consultant economics, chairman of the board of directors